Tower A : Terrace slab completed - Status as of December 2020

luxury-apartments-in-banashankari

Clubhouse : Interior works finishing 90% completed - Status as of December 2020

luxury-apartments-in-banashankari

Towers B, C & D : External painting completed. Common area finishing and flat finishing in progress completed - Status as of December 2020

luxury-apartments-in-banashankari

Towers B, C & D : External painting completed. Common area finishing and flat finishing in progress completed - Status as of December 2020

luxury-apartments-in-banashankari

7Gardens : Landscaping between A & B C D Towers in progress completed - Status as of December 2020

luxury-apartments-in-banashankari

7Gardens : Landscaping between A & B C D Towers in progress completed - Status as of December 2020

luxury-apartments-in-banashankari

Towers B, C & D Basement : Entrance Lobby finishing completed - Status as of December 2020

luxury-apartments-in-banashankari

Towers E, F & G : Structure completed. External Plastering 85% completed, External Painting & Internal finishes in progress - Status as of December 2020

luxury-apartments-in-banashankari

Towers E, F & G : Structure completed. External Plastering 85% completed, External Painting & Internal finishes in progress - Status as of December 2020

luxury-apartments-in-banashankari

Towers E, F & G : Structure completed. External Plastering 85% completed, External Painting & Internal finishes in progress - Status as of December 2020

luxury-apartments-in-banashankari

Towers E, F & G : Structure completed. External Plastering 85% completed, External Painting & Internal finishes in progress - Status as of December 2020